Custom architectural railing, integrated lighting and specialized engineering solutions come together at the Buffalo Bills’ new stadium.
The new Highmark Stadium in Orchard Park, New York, features more than 46,000 linear feet of architectural railing and over 75 custom railing styles provided by Sightline Commercial Solutions. From the seating bowl and grand stairs to premium suites, clubs and field-level areas, the project required a wide range of systems designed for different architectural, structural and functional needs.
Working with architect Populous and the Gilbane/Turner joint venture, Sightline’s scope included glass, cable and picket railing, drink rails, LED-integrated systems and specialty architectural features. The team provided budgeting, preconstruction support, structural coordination, design engineering, production and installation services throughout the project.
Custom Railing Designs for Premium Spaces and Safety
With more than 75 railing styles throughout the stadium, many of the systems required details specific to their location and application.
In the premium suites, Sightline developed custom picket railing featuring tapered profiles and a black powder-coated finish. Designed specifically for Highmark Stadium, the railing complements the suite interiors while providing the required guardrail protection.
Another custom solution addressed the angled structural columns at the back of the 400-level seating bowl. These columns presented potential climbing and head-strike hazards, so Sightline designed metal cover panels to address both concerns.
Other custom details were developed around architectural features inspired by Buffalo’s local landmarks. At a stadium installation referencing the Peace Bridge, which connects the United States and Canada, Sightline designed drink rails to complement the feature while providing a functional surface for guests and an added level of protection around the structure.
While very different in appearance and purpose, these two applications demonstrate the range of custom architectural solutions required across the stadium.
Integrating LED Lighting and Navigating Structural Challenges
Highmark Stadium incorporates both pod and strip LED lighting within select architectural railing systems. Sightline installed the lighting components into the railing assemblies at its shop before delivery, then coordinated the electrical connections with onsite trades.
At the South Overlook, an exterior gathering area, the team incorporated a specially configured LED pod to fit the rectangular top bar of the cable railing. The lighting integration also required careful coordination with surrounding construction, particularly at the stadium’s precast stairs.
Designated no-drill zones were established to protect embedded reinforcing steel. Sightline’s design team exchanged CAD drawings with other project teams to coordinate railing attachment locations and avoid conflicts with the reinforcement. Some precast stair sections had already been designed and installed, requiring the team to work around existing conditions while accommodating railing attachments and electrical requirements.
By addressing these details through design coordination, Sightline was able to develop solutions suited to the stadium’s structural conditions without compromising the intended architectural design.
Managing Material Deliveries Across a Major Construction Site
With a project of this size, getting materials to the right location at the right time presented challenges of its own. Limited laydown space meant deliveries had to be carefully planned. Incoming trucks were unloaded by third-party operators, with materials moved into temporary storage before being transported to their installation areas. Only three days’ worth of material was allowed inside the building at a time, and space became even more limited as construction progressed.
The size of the stadium made material movement especially time-consuming. Moving components into or out of the building could take much of a workday, making it important to avoid unnecessary handling. Sightline’s team worked closely with the Gilbane/Turner construction team and onsite logistics operators to coordinate deliveries and staging to ensure materials reached the appropriate installation areas when crews were ready for them. The just-in-time delivery process required ongoing coordination as construction progressed and available space changed throughout the project.
Architectural Systems Throughout the Stadium
Sightline’s work extends across the stadium’s public, premium and operational areas, with different railing systems selected to meet the requirements of each space.
Glass railing maintains open views throughout the venue, while cable and picket systems provide protection along stairs, concourses and seating areas. Drink rails add functional surfaces within premium and social environments, and LED-integrated railing brings lighting directly into selected architectural features.
The combination of these systems required attention to different mounting conditions, materials, finishes and installation requirements across the project. From custom suite railing and column covers to integrated lighting and extensive stadium-wide railing, the work brought together Sightline’s design engineering, craftsmanship and installation capabilities.
Bringing the Details Together
Highmark Stadium required a broad range of architectural systems, but the challenges went well beyond the quantity of railing installed.
Custom designs had to fit the stadium’s architecture, attachment details needed to account for structural conditions, lighting required coordination with electrical trades, and material deliveries had to be managed within a tightly controlled construction site.
With more than 46,000 linear feet of railing and over 75 custom styles, Sightline’s work is incorporated throughout the Buffalo Bills’ new home, supporting the safety, functionality and guest experience of the stadium.