Hard Rock Stadium (Miami Dolphins)

Luxury seating areas and custom railing maximize electric environment

Completed: September 2015
Location: Miami, Florida
Architect: 360 Architecture
Contractor: Hunt Construction Group

Collaborated with architects and owners to accommodate a fast paced schedule by designing, engineering, manufacturing and installing over 16,000 linear feet of aluminum base shoe, anodized aluminum post supported railing with glass infill and cable railing within an 8 month time frame. Over 2,100 sq. ft. of large forkliftable seating platforms make up four seating sections in the Field Club seating areas bringing luxury seating areas at both end zones down to field level. Portable step, ramp and camera bay infill units were also provided.